Town Council   |   Mayor's Office   |   Staff Directory   |   Departments   |   Boards   |   Emergency Info   |   E-mail News   |   Beach Renourish
Town Ordinances   |   Document Index   |   Floodplain Info   |   Recycling   |   Canals / Bulkheads   |   P.O.A.   |   Local Links
Resource Links   |  HOME
Natural Canals

 

Click here to view the As-Built Survey for the  Maintenance Dredging of the Natural Canals

 

March 27, 2008

 Canal Dredging Project Update

The dredging has been completed on Canal 14 (between Wilmington and Concord Streets), Canal 20 (adjacent to the disposal site by Lee Street) and Canal 3 (Eastern Entrance to Concrete Canals and a portion of the Canal located between Moore and Cumberland Streets).  Boats are now allowed to re-enter these areas. 

I would like to take this opportunity to thank the property owners on the Natural Canals for their cooperation during this dredging project. 

                                                  Daisy Ivey
                                                  Town Administrator

 

March 17, 2008

Canal Dredging Project Update

Canal 15 has been surveyed by the Engineer and the Contractor has confirmed that all piping and equipment has been removed from this canal.  Therefore, boats are allowed to re-enter Canal 15 at this time. 

The Wildlife’s boat ramp has been dredged, however it may be necessary that Marcol Dredging will revisit this area to perform additional dredging.  If the Contractor does return to this area, pipeline would be crossing the entrance of Canals 15, 16, 17 and the Commercial Canal.  We will notify you of this schedule as soon as possible.  All boaters should proceed with caution when entering and leaving these canals.  Boaters may need to contact the Dredge directly to make arrangements for the pipe to be lowered if necessary. 

                                                   Daisy Ivey
                                                   Town Administrator

 

March 4, 2008

Canal Dredging Project Update

The dredging has begun in Canal 14 (between Wilmington and Concord Streets).  The second dredge has finished Canal 20 (adjacent to the disposal site by Lee Street) and will begin in Canal 3 next.  Canal 3 consists of the Eastern Entrance to Concrete Canals and a portion of the Canal located between Moore and Cumberland Streets. Canal 15 (between Fairmont and Wilmington Streets) is scheduled to be surveyed this week.  It is very important that boaters do not enter Canal 15 until the surveying has been completed. 

                                                   Daisy Ivey
                                                   Town Administrator

 

February 22, 2008

Canal Dredging Project Update

The Contractor is currently dredging Canal 22 (Commercial Canal) and will remain in this canal for an additional seven (7) or eight (8) days.  The dredge will then move to the North Carolina Wildlife Boat Landing while the Engineers are surveying Canals 21, 22 and 23.  It is anticipated the dredging of the boat landing will be approximately two (2) to three (3) days.  The dredge will then proceed to Canal 14 approximately March 5th.  The second dredge has been utilized for pumping.  

                                                   Daisy Ivey
                                                   Town Administrator
 

February 18, 2008

Canal Dredging Project Update

The dredging has been completed in Canals 16 and 17.  Both Canals 16 and 17 have been surveyed by the Engineer and the Contractor has confirmed that all piping and equipment has been removed from these canals.  Therefore, boats are allowed to re-enter Canals 16 and 17 at this time.

Canal 15 has been dredged, however, this canal has not been surveyed.  The Contractor still has equipment and pipe in this canal.  For these two reasons, it is important that boaters do not enter Canal 15 at this time. 

The Contractor is currently dredging Canal 22 (Commercial Canal).  The second dredge is planned to begin working in Canal 20 adjacent to the disposal site at the beginning of next week.  If dredging conditions change, the second dredge will be taken from dredging Canal 20, and be used as a booster pump for the first dredge working in the Commercial Canal. 

All boaters should proceed with caution when entering and leaving all canals.  Currently pipeline extends from the Commercial Canal along the Intracoastal Waterway all the way to the disposal site, so pipeline crosses the entrance of each canal.  It cannot be predicted at exactly what depth the pipe will be.  However, at times when dredging operations are on hold, the pipe is much more likely to be at or near the surface.

Any time a boater needs to enter or leave a canal, they need to touch base with the Dredge directly so that they can lower the pipe if need be.  Boaters are asked to kindly contact the Dredge Operator for Marcol Dredging directly on Channel 66. Also, the dredge operator can be contacted by phone at (910) 269-8427.  By the boater contacting the Dredge and reporting their intentions, the Dredge can then determine if the pipeline will be a hazard and can shut down the dredge plant so that the pipe can be lowered.

                                                   Daisy Ivey
                                                   Town Administrator

 

February 7, 2008

Canal Dredging Project Update

Dredging has been completed for Canals 16 and 17.  Homeowners will be allowed to return their boats back to Canal 17 after February 8th and to Canal 16 after February 12th. 

Marcol has brought in a second dredge that will be utilized as a booster pump.

The latest schedule and plan is to continue as follows: 

               Canal 15: Begin Saturday Feb. 2 and continue until 
                                Sunday, February 10.

               Commercial Canal:  Begin Monday Feb. 11, 
                                expected duration 7-8 days. 

When dredging begins on the Commercial Canal, it will be necessary for the dredge pipe to be laid at the mouths of the canals beginning at the Commercial Canal extending to the spoil site. 

After the dredging of these canals the plan could change, however, it is likely that one dredge will return to Canal 15 to complete this area, while the second dredge works adjacent to the disposal site. 

                                                                            Daisy Ivey
                                                   Town Administrator

 

January 15, 2008

IMPORTANT NOTICE TO PROPERTY OWNERS
Canal Dredging Project Update

According to Marcol Dredging, there are still five (5) boats in Canal 16 which impede dredging activities.  Since they planned to begin with this canal, they have moved their dredge and adjusted their schedule.  The dredging will now begin on Canal 17 on January 16th.  However there is still one (1) boat in the water at Canal 17 which will need to be moved.  After starting with Canal 17 tomorrow, they will move to either the Commercial Canal or Canal 16, and then resume the schedule originally submitted.  In order for the project to proceed without interruptions, it is imperative that property owners remove all boats and secure loose items.  Boats on lifts that protrude past the dock line will interfere with the dredging project and must be removed.

                                                   Daisy Ivey
                                                  Town Administrator

_____________________________________________________________________

January 8, 2008

Canal Dredging Project Update
(Including Schedule and Cost Information) 

            The contract for the 2007 Maintenance Dredging project has been awarded to the low bidder – Marcol Dredging Company, Inc.  Marcol Dredging has mobilized to our area and anticipates dredging will begin on Saturday, January 12th, depending on completion of earthwork at the disposal area.

            Marcol Dredging has indicated work will begin on January 12th in Canal #16 (Between Monroe and Fairmont Streets) and then proceed consecutively to the following canals.  It should take approximately 7 to 10 days per each 2000 feet of canal.
                                    Canal 17 (Between Monroe and Laurinburg)
                                    Canal 22 (Commercial Canal)
                                    Canal 21 (Canal westward of Laurinburg)
                                    Canal 23 (Connector Canal between Canals 21 and 22) 

            It is possible that a second dredge will be utilized simultaneously in the remaining canal order.

                                    Canal 15 (Between Fairmont and Wilmington)
                                    Canal 14 (Between Wilmington and Concord)
                                    Canal   8 (Western Entrance to Concrete Canals)
                                    Canal   3 (Eastern Entrance to Concrete Canals and
                                                     portion of Canal located between Moore and
                                                     Cumberland)
                                    Canal 20 (Canal adjacent to Disposal Area)

            It is very important that affected property owners take necessary action immediately to secure any loose items and move all boats away from the outside face of their docks.
 

            The total cost associated with this dredging is projected to be $1,078,929.36.  Of this amount the Natural Canal Tax District is responsible for $753,758.96.  Other funds will be paid as follows: 

·        Town of Ocean Isle Beach – Payment of entire cost   -   $40,207.14
associated with Entrance Canals #8 and #3

·        Concrete Canal Special Tax District – Payment of     -  $278,131.95
cost associated with Canal #20 (Adjacent to Disposal
Area as well as the portion of Concrete Canal #3
being dredged located between Moore and
Lumberton Streets)

·        Reimbursement for Wildlife Resources Commission   -  $6,831.31
for Dredging at Boat Ramp

            Photographs and video of all canals will be taken prior to the beginning of construction.  Please remember the Town nor the contractor will be responsible for pilings not properly installed.  According to our engineer properly installed means that pilings must be installed below the six (6) feet dredge limits.    Canals will be dredged to -6.0 mwl with widths varying from 20 to 40 feet depending on the individual canals.  A copy of plans is available for review at Town Hall between the hours of 8:00 a.m. until 5:00 p.m. Monday through Friday. 

                                                                                    Daisy Ivey
                                                  Town Administrator

_____________________________________________________________________

December 31, 2007

The Town of Ocean Isle Beach anticipates awarding the contract for the 2007 Maintenance Project for the Natural Canals on January 2, 2008.  The scope of this project includes dredging along the following areas: 

  • Four residential canals located between Laurinburg and Concord Street
  • Commercial canals located between Causeway Drive and Laurinburg Street
  • Entrance canals located between Union & Raeford Street and Moore & Cumberland Street
  • Approximately 450 feet of the entrance of the canal located between  Moore & Cumberland Street
  • A portion of the western header canal located adjacent to the special disposal site

In anticipation of the commencement of this project, the Town is requesting that all affected property owners secure any loose items and move all boats away from the outside face of their docks.  It is estimated that construction will occur between January 10 and April 30, 2008.  As soon as the Town receives a definite schedule from the contractor indicating date and particular locations for dredging, the Town will post this information on the Town’s website and as well as Channel 8.  Please visit our website at www.oibgov.com for this information. 

Please remember that if pilings are uncovered during this project, it will be the responsibility of the homeowner to reinstall these pilings.  Neither the Town nor the contractor will be responsible for pilings not properly installed. 

We look forward to the commencement of this project.  If you have any questions or need additional information, please do not hesitate to contact our office.

                                                                                       Daisy L. Ivey
                                                    Town Administrator

_____________________________________________________________________

UPDATE - December 6, 2007

2007 Maintenance Dredging Project 

            The 2007 Maintenance Dredging Project for the Natural Canals has now been officially advertised and bid proposals will be received by the Town on December 20, 2007.  The scope of this work estimates dredging approximately 55,270 cubic yards of unclassified dredging and disposal along approximately 18,500 linear feet of residential and commercial canals in the following areas: 

  • Four Residential Canals (Canals #14 to #17) located between Laurinburg and Concord Streets
  • Commercial Canals (Canals #21, #22 and #23) located between Causeway Drive and Laurinburg Street
  • Entrance Canals located north of Canal #8 and #3 (between Union and Raeford Streets and Moore and Cumberland Streets)
  • Approximately 450 feet of the entrance of Canal #3 (located between Moore and Cumberland Streets)
  • A portion of the western header canal (Canal #20) extending from approximately the center of Canal #3 (between Moore and Cumberland Streets to the western end) This is the section of canal located adjacent to the spoil disposal site.

A copy of the final drawings is available for additional informational purposes.  (CLICK HERE TO VIEW FINAL DRAWINGS) Final permit issuance for this project is expected within the next 3 – 4 weeks.  This site will be updated as additional information is available. 

                                                      Daisy Ivey
                                                      Town Administrator

_____________________________________________________________________

The Town, in the fall of 2000, adopted a minimum design criteria for the vertical wooden bulkheads. This purpose of which is to make sure that the interests of the property owner is protected. Below you will find the adopted construction plans and spec sheet for the wooden bulkheads. All documents are in Adobe Acrobat format, unless you specifically choose the HTML format.
Up to a 4 foot Bulkhead (HTML) Up to a 6 foot Bulkhead (HTML)
Up to a 8 foot Bulkhead (HTML) Up to a 10 foot Bulkhead (HTML)
Specifications and Notes (HTML)

Ocean Isle Beach Town Hall
Three West Third Street
Ocean Isle Beach, NC 28469
910-579-2166
910-579-8804 fax
Email Town Hall