UPDATE - December 6, 2007
2007 Maintenance Dredging Project
The 2007 Maintenance
Dredging Project for the Natural Canals has now been officially advertised and
bid proposals will be received by the Town on December 20, 2007. The scope of
this work estimates dredging approximately 55,270 cubic yards of unclassified
dredging and disposal along approximately 18,500 linear feet of residential and
commercial canals in the following areas:
- Four Residential Canals
(Canals #14 to #17) located between Laurinburg and Concord Streets
- Commercial Canals (Canals
#21, #22 and #23) located between Causeway Drive and Laurinburg Street
- Entrance Canals located
north of Canal #8 and #3 (between Union and Raeford Streets and Moore and
Cumberland Streets)
- Approximately 450 feet of
the entrance of Canal #3 (located between Moore and Cumberland Streets)
- A portion of the western
header canal (Canal #20) extending from approximately the center of Canal #3
(between Moore and Cumberland Streets to the western end) This is the section
of canal located adjacent to the spoil disposal site.
A copy of the
final drawings is available for additional informational purposes. (CLICK
HERE TO VIEW FINAL DRAWINGS) Final permit issuance for this project
is expected within the next 3 – 4 weeks. This site will be updated as
additional information is available.
Daisy Ivey
Town Administrator
UPDATE
In February 2002, the Town completed the Natural Canal Dredging Project. This project consisted of a 40 foot wide 6 foot deep box cut.
At the February 8, 2005 Board of Commissioners meeting, the Board voted
unanimously to approve an engineer proposal to obtain hydrographic surveying
along with engineering fees for maintenance dredging of approximately 18,500
linear feet of dredge area. This area consists of four residential canals
located between Laurinburg and Concord (Natural Canals), commercial canals
located between Causeway and Laurinburg as well as the entrance canals located
between Raeford and Union Streets and Cumberland and Moore Streets respectively.
In addition, this project would include a portion of the western end of the
header canal. |